TL;DR

  • Three US reactors are trying to come back from shutdown, backed by up to $4.4 billion in federal loans, per the AP. Buyers are signing for a start date with no track record, and Palisades' co-ops signed for 28 years against a license that runs to 2031. The thread supplied what the post left out: decommissioning has stages, none of the three had been dismantled, and the contract can price the date directly.

  • PJM has 7 GW of approved battery and hybrid projects still unbuilt. The queue was supposed to be the hard part; the post argues the binding constraint is now revenue a lender can bank on, because the capacity auction's price collar, its cap and floor, covers only auctions through the 2029/30 delivery year.

  • Paid readers get the practitioner exchange on how batteries can earn without the capacity auction, who the PJM post reached, and Field Notes on PG&E's two burial costs, state energy machinery and the 1893 railroad precedent.

---

This week's two signals are about commitments signed against dates and rules nobody can yet see: a restart contract that outlasts the reactor's license, and a battery financed today against a capacity auction whose price cap and floor end with the 2029/30 delivery year.

Coverage This Week

  • Europe could buy cheaper wind turbines. It mostly doesn't - European makers supplied 94.5% of Europe's 2025 installations while Chinese rivals cost at least 30% less; bidders should watch how much weight each auction puts on non-price criteria. Read →

  • A closed Michigan reactor owes its buyers power by March 2027 - no US reactor has restarted after entering decommissioning, three are trying, and anyone buying their power is buying a date with no track record. Read →

  • Buried power lines are the surest fire fix and the costliest - PG&E's burial plan carries two capital figures, $11.4 billion and $16.6 billion, and which one enters the benefit-cost ratio is the regulatory fight. Read →

  • Congress got the headlines. States hold the energy levers - with federal rules hard to underwrite, the post argues for sorting states by machinery rather than party: who picks the regulator and who pays for new load. Read →

  • If clean power is a hedge, the CFO is the buyer - the number of US companies signing offsite clean power contracts halved to 33 last year, per BNEF, while volume hit a record; a hedge buyer needs the contract to pay out in the hours its bill hurts. Read →

  • The biggest US grid has 7 GW of approved batteries unbuilt - PJM's projects already cleared the queue; the post argues the constraint has moved from permission to bankable revenue. Read →

  • Union Pacific went broke in 1893. Its trains kept running - AI data center investment is projected at about 3.6% of GDP a year to 2032, above the railroad era; if it overshoots, the stake is who owns the power and buildings next. Read →

This Week’s Signals

Each signal below traces the practitioner debate on two of the week's posts and who the post reached. Audience figures come from LinkedIn's viewer demographics for each post; industry comparisons are against earlier posts on the same topic and are stated as upper bounds. Who reads a post is attention, not demand.

A Restart Sells a Date, and the Contract Decides Who Waits

Three US reactors are trying to do what no American plant has done: return to service after entering decommissioning. They are Palisades in Michigan, Crane (the former Three Mile Island Unit 1) in Pennsylvania and Duane Arnold in Iowa. The Energy Department is lending up to $4.4 billion across them, for about 2.25 gigawatts, per the AP. The closest precedent, Browns Ferry Unit 1 in Alabama, sat idle 22 years but never entered decommissioning; TVA brought it back in 2007 for roughly $1.8 billion, and its inspector general later traced post-restart reactor trips mainly to one fitting installed wrong. In the post's framing, the risk doesn't end at the first start. It moves from the construction schedule into the operating record.

Palisades shows the schedule side. Its target slipped from 2025 to early 2026; fuel loading began August 30, then one fuel assembly tilted in the reactor vessel, and Holtec recovered it in October after an expedited approval from the Nuclear Regulatory Commission (NRC). On October 29, Energy Secretary Chris Wright said the restart may be only weeks away, per Michigan Public. The quieter exposure is the contract term. The two rural co-ops taking Palisades' output signed for an initial 28 years, and the plant's license runs to 2031, so most of that term rests on a subsequent license renewal, which the NRC has given Holtec until March 2028 to file. Crane's buyer is Microsoft, on a 20-year deal targeting 2027 and still awaiting NRC approval; Duane Arnold's is Google, on a 25-year deal aiming for early 2029.

Of 57 comments, the most useful went where the post didn't. On the word "decommissioning," a nuclear project manager argued the restart plants sit in an earlier stage: "There’s different levels of decommission. The plants that are being restarted were in SAFESTOR. Basically extended cold shutdown with reduced maintenance on NSSS and safety systems required for greater than Mode 0 operations." A nuclear services professional pointed to Kewaunee in Wisconsin, which never came back: "Dominion almost immediately began dismantling Kewaunee after shut-down. The sold the transformers very quickly, followed by wrecking the BOP side of the plant." Kewaunee was formally in SAFSTOR under Dominion too, per the NRC; its large-scale dismantling came after a 2022 sale, so the label alone didn't settle whether it could return. One commenter said the 22-year idle unit was Watts Bar, not Browns Ferry. The post's precedent holds: Browns Ferry Unit 1 shut in 1985 and restarted in 2007, while TVA's Watts Bar Unit 2 was a halted construction project finished in 2016, not a restart. A human factors engineer pushed back on the post's "no track record" framing from the other side: restarts are quickest "Because you have a documented operating history." As the engineer put it, "The plant is sitting there; it’s not on paper with a design that may be based upon equipment that is yet to be fabricated."

On the contract, a corporate procurement lead offered a structure: "Jamie, buyers in that spot can price the date, not just the megawatts. A price that steps down for each month of delay, or the right to source part of the volume elsewhere until the unit runs, puts the start-date risk with the party that controls it." An energy sector professional on the retail side asked the matching question: "Do the Palisades co-op contracts carry a replacement power clause if March 2027 slips, or does the buyer simply wait?" A practitioner who plans water and power for data center sites added where restart schedules tend to slip: "Systems that sat idle get flushed, tested and refilled, and water permits written for a running plant may need renewing or amending. Restart dates, like data center dates, often turn on water work that never makes the headline." Another commenter recalled that a derecho wrecked Duane Arnold's cooling towers and hastened its shutdown; the August 2020 storm brought forward a closure already planned for that autumn. Much of the rest of the thread argued nuclear safety and waste rather than the restarts.

Our read: "decommissioning" means two things. It is a licensing status: once an owner certifies permanent shutdown and fuel removal, the license no longer allows operation, and a restart needs the NRC to restore it. It is also a physical state, and the formal label matters less than what was physically removed. That turns diligence into an inventory: which systems were mothballed, which were sold or stripped, which permits lapsed, and which NRC approvals the restart still needs. The engineer's point sharpens the risk rather than removing it: these units have operating records; what none of them has is a record of coming back. The thread also put the two exposures on different timelines. The start date can be priced now, through delay step-downs or replacement-power rights. The license runway is a longer bet. Most of a 28-year term depends on a subsequent renewal being filed and approved, and even a granted renewal would run to 2051, short of the contract's end. A buyer can still price that, through rights to cut volume or exit if the renewal is denied or delayed, but only if the contract says so.

The post reached far past its usual audience. Impressions reached 130,024, more than eleven times the average for earlier nuclear posts, and 98% came from outside the author's network. Oil and Gas viewers were 17% of the audience, against at most 9.5% on earlier nuclear posts, and Construction viewers 7%, against at most 3.37%. CXO and VP viewers were 13%, below the 17.6% 90-day average, and saves ran below the 90-day average rate: wide reach rather than a concentrated senior audience. (Composition: Oil and Gas 17% vs up to 9.5%; Construction 7% vs up to 3.37%; CXO/VP 13% vs 17.6%; impressions +1,066.3% vs topic norm.)

> Does Palisades reach commercial operation before the March 2027 delivery date, and does Holtec file the subsequent license renewal, due by March 2028, that most of the co-ops' 28-year term depends on?

PJM's 7 GW: Approval Stopped Being the Hard Part

PJM, which serves over 67 million people from Chicago to Washington, has 7 GW of approved battery and hybrid projects still unbuilt. It tapped emergency supplies on a record 16 days this year, per Bloomberg, and from June to mid-September its Western hub averaged 53% above a year earlier, while Dallas fell 13%. Gas prices, weather and data center load drive much of that gap. The part market design controls is storage: Texas now runs 24.5 GW of batteries, more than double 18 months ago, and California has over 17 GW. For years PJM's story was the queue. These projects already cleared it.

The post traced the gap to how each market pays a battery. Texas lets batteries earn from price swings and grid services and connects new projects quickly. California ordered its utilities and other buyers in 2021 to procure 11.5 GW of new capacity on a fixed schedule, so developers built against signed contracts. PJM runs a big part of the revenue case through its capacity auction, where a four-hour battery is credited at 58 to 59% of its size in the 2027/28 auction, a figure PJM recalculates for each auction. The auction has cleared at its price cap three times running, and that cap covers auctions only through the 2029/30 delivery year. FERC approved extending the price collar to that auction in April, per the American Public Power Association; the auction closes December 15. Capacity revenue a few auctions out is never known when a battery is financed. What is new is that the cap and floor end with this auction and PJM hasn't said what replaces them, so a battery financed today has to earn well past 2030 under rules that are still open.

Behind the paywall: the practitioner exchange on how a battery can earn without the capacity auction, why one originator credits Texas's land and market structure, the state route already open inside PJM, who the post reached, and Field Notes.

A battery contractor offered a route around the auction: "Contracted value instead of merchant value. Behind-the-meter storage at military bases, hospitals and data centers can be paid through energy savings performance contracts, demand-charge savings and resilience requirements. Those cash flows don’t depend on where PJM’s capacity rules land after 2030." A power originator pointed to Texas's head start: "Cheaper/available land played a big role in ERCOT BESS growth as did avoiding barriers created by PJM vertically integrated utilities IMHO." Another commenter extended the bankability point down the supply chain: "The bankability gap can also stall suppliers and contractors well before a project reaches financing." Several other replies argued gas versus batteries rather than the market rules, and no one in the thread named the PJM rule change that would move most of the 7 GW first.

Our read: the contractor's route works for some of the 7 GW, not most of it. Behind-the-meter contracts swap auction risk for one customer's credit and load, and they suit smaller projects sited at that customer. Grid-scale projects that cleared PJM's queue were sized for the wholesale market, and their lenders need either a post-2030 capacity rule or a long contract with someone creditworthy. The California route the post described already exists in part inside PJM: states including New Jersey and Virginia have set storage targets or procurement programs, and contracts under them are the kind of bankable revenue the auction doesn't provide. For grid-scale storage, the post-2030 answer may come from statehouses before PJM, which is the states Field Note's argument applied to batteries. That makes the December 15 auction less about its clearing price, which the collar bounds, than about what PJM says it will do once the collar ends. Accreditation itself also moves with each auction, a separate risk for lenders. And the supply-chain point means the delay compounds: a project waiting on its revenue case is also holding its contractors and equipment orders in place.

The post reached a wider and more utility-heavy audience than most grid posts, with fewer reactions. Impressions reached 8,510, about 47% above the average for earlier grid posts, and 91% came from outside the author's network; it drew 23 reactions, against an average of 67. Utilities viewers were 13% of the audience, against at most 5.84% on earlier grid posts, and Renewable Energy Power Generation viewers 6%, against at most 3.66%. CXO and VP viewers were 20%, against the 17.6% 90-day average. (Composition: Utilities 13% vs up to 5.84%; Renewable Energy Power Generation 6% vs up to 3.66%; CXO/VP 20% vs 17.6%; impressions +47.5% vs topic norm.)

> Does the December 15 auction clear at the cap a fourth time, and does PJM publish a post-2030 capacity design before lenders have to price the 2030/31 auction without a collar?

Field Notes

  • PG&E's two burial costs: PG&E plans to bury about 5,000 miles of line by 2037 for about $11.4 billion and values the benefits at $117 billion, over ten times the cost. Its quarterly investor filing puts the same plan at $16.6 billion of capital if fully approved, which would cut the ratio to about seven. The filings don't reconcile the two. Approved capital enters the rate base, where regulators currently allow PG&E just under 10% on the equity, while the roughly $6 billion of avoided tree trimming the plan counts is expense recovered at cost. In 2023 California's ratepayer advocate said the cost of one buried mile covers almost four miles of insulated overhead wire. In the thread, a consultant raised what the benefit model may not price: underground networks need more switching points because faults are harder to find and slower to repair, and an earthquake that faults several buried sections at once could leave parts of the grid out for "an unacceptably long time." A CPUC proposed decision on October 16 did not adopt most of the utilities' joint proposals on cost method; it is not final. Read →

  • Sort states by machinery, not color: with a federal rule written by one administration and reversed by the next hard to underwrite, the post argues statehouses now hold the decisions underneath. Wood Mackenzie says states have "broad statutory authority over retail electricity, utility regulation, and siting," and Debtwire counted 30 data center laws across 16 states by mid-June. The post's filter: who picks the regulator, whether the governor has the legislature, whether utilities own generation or buy from a market, and whether a proposal changes who pays for new load. The retail-side professional quoted in the restart thread tested it on Texas: ERCOT's April filing showed 367,790 MW of demand by 2032, while the Texas peak has grown about 2.4 GW a year, from 74,533 MW in 2019 to 91,075 MW this July, on EIA's hourly basis. "A rule that has large loads pay for their own wires and sit out the tight hours is easier to underwrite than a pause with no end date," the commenter wrote. January's legislative sessions are the post's first test. Read →

  • The track outlasted its owners: a Brookings paper by Columbia's Stijn Van Nieuwerburgh projects about $10.3 trillion of US AI data center investment from 2025 to 2032, roughly 3.6% of GDP a year, against about 2.2% for railroads from 1870 to 1890; the paper notes the historical figures aren't perfectly harmonized, so read it as scale. In 1893 more than 27,000 miles of US track went into receivership; Union Pacific came out in 1898 under new control, the original investors took the loss, and the trains kept running. In the paper's model about a third of a data center's cost is the building and its power infrastructure, built to outlast several generations of chips. A capital-markets commenter drew the line the analogy needs: the track surviving "did not protect the investors who financed them," and the residual value of a powered site "depends on location, electricity pricing, connection rights, future customer demand and the cost of adapting the facility to new technology." The post's test for anyone financing the power side: what would a second owner pay for the powered site with today's tenant gone? Read →

---

The thread running through this week: a commitment that runs longer than the rules beneath it. A restart contract runs 28 years against a license that ends in 2031; a battery financed today needs revenue past an auction cap that ends in 2030; a powered data center has to be worth something to an owner nobody has met yet. If you hold one of those commitments, the question is which part of its term rests on a filing, a rule or a buyer that doesn't exist yet, and who carries the gap if it never arrives.

Reply if any of this is playing out at your company, or contradicting what you're seeing on the ground. Every reply goes directly to our analyst desk and feeds our intelligence.